What is Earned Value Management (EVM)?

Format: Other

Academic level: College

Paper type: Math Problem

Words: 266

Pages: 1

Downloads: 0

When you collect the earned value data for your project, you get the following data: PV = $1,500,000, EV = $ 1,200,000, AC = $1,000,000. You expect the factors for cost variance to continue in the same way in future. The value of the remaining work is $1,000,000. What should be the new EAC for the project? 

Therefore; 

The latest earned value report of the project shows CPI = 1.2, SPI = 0.8, PV = $500,000, SV = - $220,000. What is the cost variance of the project? 

It’s time to jumpstart your paper!

Delegate your assignment to our experts and they will do the rest.

Get custom essay

3. When you analyze earned value data for your project, you get the following information: CPI = 0.84, and the EV is $48,000. How much money has actually been spent on the project? 

Rewriting the equation; 

The earned value data for a project has been derived as follows. PV=$400,000, EV=$400,000, AC =$600,000. What is the burn rate of the project? 

You are managing a construction project. You have completed half the project work. The total planned cost at this stage is $1,000. The actual work that has been completed at this stage is worth $1,200. You have spent $1,500 already on the project. What is the CPI? 

You perform an earned value analysis for your project, resulting in the following numbers: 

EV: 354,000; PV: 454,000; AC: 474,000. Which results are correct? 

A. CV: +120,000; SV: +100,000 

B. CV: +100,000; SV: +120,000 

C. CV: -100,000; SV: -120,000 

D CV: -120,000; SV: -100,000 

The correct answer is D. 

7. You are managing a software project with an initial budget estimate of 2 million USD. During interim cost and schedule performance analysis, you figured out that: 

Initial Budget Estimate = $2,000,000 

    You should have spent $500,000 till now based on your initial plans and 1000 man/days of schedule activities. 

    You spent $600,000 till now and completed 1100 man/days of schedule activities which should have cost $450,000 based on your initial plans. 

    You re-estimated the budget required for the remaining work to be done as $1,500,000. 

What is the CPI and SPI of the project respectively? 

8. What is the CV and SV of the project respectively? 

9. What is the variance at completion? 

10. What is the TCPI based on your new estimate at completion value? 

Illustration
Cite this page

Select style:

Reference

StudyBounty. (2023, September 14). What is Earned Value Management (EVM)?.
https://studybounty.devstage.cloud/what-is-earned-value-management-evm-math-problem

illustration

Related essays

We post free essay examples for college on a regular basis. Stay in the know!

17 Sep 2023
Maths

Bernhard Riemann's Life and Contribution to Mathematics

Introduction Riemann Bernhard was an extraordinary mathematics professor at Göttingen, where he did most of his work in geometry, number theory, real as well as complex analysis. Having a strict Christian...

Words: 2630

Pages: 12

Views: 46

17 Sep 2023
Maths

How to Solve Problems: The 4-Step Problem Solving Process

Lesson Topic: Addition and Subtraction Grade: K-2nd Subject: Math Time: 40 minutes Introduction Problem solving provides a framework for developing higher-order thinking skills. However, many students...

Words: 598

Pages: 2

Views: 449

17 Sep 2023
Maths

What is the Goodness of Fit Test?

Null hypothesis, H0: The candies are uniformly distributed Alternative hypothesis, H1: The candies are not uniformly distributed. Chi-square = } Degrees of freedom = No. of groups-1= 6-1 =5 =0.0

Words: 79

Pages: 3

Views: 83

17 Sep 2023
Maths

Managerial Ethics in Financial Analysis and Accounting

Companies try to increase their value by using effectively all the resources provided to them by regulators, debtors, and shareholders. Mangers have fiduciary responsibilities and duties, which affects how they...

Words: 276

Pages: 1

Views: 59

17 Sep 2023
Maths

Using and Understanding Mathematics: Prologue Order of Operation

Order of operations involves addition, subtraction, multiplication, division, squaring, and more. The importance of the concept is understanding the order in which to solve a problem. If you calculate in the wrong...

Words: 143

Pages: 1

Views: 416

17 Sep 2023
Maths

Workplace Diversification at Coca Cola

The idea of incorporating both domestic and international clients has created a need for businesses to diversify their workforce. In the past decades, the nature of various workplaces featured members of a similar...

Words: 926

Pages: 3

Views: 92

illustration

Running out of time?

Entrust your assignment to proficient writers and receive TOP-quality paper before the deadline is over.

Illustration