Earned Value Management

Format: APA

Academic level: College

Paper type: Coursework

Words: 685

Pages: 4

Downloads: 0

Updated status report 

The efficient determination of a project’s performance and progress often requires the analysis of a wide range of factors that usually shall include the scope of the project, the costs accrued in the implementation of the project and the time taken to complete the project (Fleming and Koppelman, 2002). The first thing that is conspicuously lacking from the report is the earned value of tasks A and B. The determination of this figure should be the indicator of the progress of the project so far. The table below computes the actual earned values for both tasks and shall be used as evidence of the errors in the status reports given by Jennifer and Ben. 

Task  Budgeted work/cost  Actual work/ cost to date  Percent work complete  Earned value of the tasks  Estimate to complete  Planned start date  Actual start date  Planned end date  Projected end date  Planned resource utilization  Actual resource utilization 
A  120 hrs./$1200  60 hrs./$600  30%  $360  90hrs./$900  March 15  March 30  June 15  June 15  25%  30% 
B  120 hrs./$1200  50 hrs./$500  30%  $360  60hrs./$600  April 1  April 8  May 15  May 30  50%  30% 
It’s time to jumpstart your paper!

Delegate your assignment to our experts and they will do the rest.

Get custom essay

The progress on the task A is actually of great concern. Jennifer’s assessment might have arisen from the fact that 50% of the allocated costs of the project had already been spent on the project. The actual earned value in the task is however, $360 which translates to 30% of the allocated cost. This means that the project is significantly over budget. The level with which this is above the budget is further shown in the review of the amount that is projected to be spent to complete the project. The resource utilization for task A is also higher than the planned resources. 

Task B is however in line with the budgetary allocations here, and doing better than expected. At 30% completion, it is estimated that it will be completed at a cost $100 less than the budgeted cost.it is however set to be completed at an additional period of 15 days which presents another overrun in terms of the value of time. Hence the project will be behind schedule. The forecasts for the tasks can however be regarded as unreliable since they don’t consider the actual performance of the project so far. 

Instructions on how to determine and present the next project update. 

Given the project plan, the most significant things that have to be put into perspective are the time constraints of a task and the cost of the task. The final goal usually is the provision of an accurate forecast of the performance of the task or project at hand (Vanhoucke, 2013). The valuation and the set time are the first variables to be considered. With these values the following can be accurately worked out in a systematic manner to give the best estimate of the project performance over time (Reichel, 2006). 

The project plan. 

This refers to the initial plan or schedule for a task. It is from this template that one can record the progress of the task and further determine the success of the task so far (Lipke, Zwikael, Henderson and Anbari, 2009). The project plan has a set period for the performing of the task alongside the cost of the project. The running of the cost of the project against timing yield the planned values of the project. These values can be surpassed or turn out to be less depending on the efficiency of the work done (Reichel, 2006). They cat as a bench mark to determine the success of the project. 

The Earned Value or the Budgeted Cost of work performed. 

The earned value is determined from the percentage of the task accomplished. It is calculated by multiplying the percentage work done by the budgeted cost of work. It is meant to determine the amount of money that should have been spent in the accomplishment of the task. Depending on the amount, it can be determined whether the task being implemented according to the set schedule (Vanhoucke, 2013). These values can then be used to project the time it would take to accomplish the task and the cost that will be accrued. 

References. 

Fleming, Q W and Koppelman, J M. (2002). Earned Value Management: mitigating risks associated with construction projects. Risk Management . Retrieved from http://s3.amazonaws.com/academia.edu.documents/32040257/Earned_Value_QuentinFleming.pdf?AWSAccessKeyId=AKIAIWOWYYGZ2Y53UL3A&Expires=1500301555&Signature=y6YJRlTfyXRlHEYcV8eQwdO8mf4%3D&response-content-disposition=inline%3B%20filename%3DP_M_M_A_R_C_H_-A_P_R_I_L_2_0_0_2_Earned.pdf . 

Lipke, W, Zwikael, O, Henderson K and Anbari F. (2009). Prediction of project outcome: The application of statistical methods to earned value management and earned schedule performance indexes. International Journal of Project Management, Vol 27, Issue 4, pp. 400-407. 

Reichel, C. W. (2006). Earned value management systems (EVMS): "you too can do earned value management" Paper presented at PMI® Global Congress 2006—North America, Seattle, WA. Newtown Square, PA: Project Management Institute. 

Vanhoucke, M. (2013). Earned Value Management. Project Management with Dynamic Scheduling , pp. 217-240 

Illustration
Cite this page

Select style:

Reference

StudyBounty. (2023, September 15). Earned Value Management.
https://studybounty.devstage.cloud/earned-value-management-coursework

illustration

Related essays

We post free essay examples for college on a regular basis. Stay in the know!

How AI Can Help Retailers Solve Business Problems

The global marketplace is currently more integrated than ever before. This situation presents a never-before experienced opportunity for retailers. Multinational organizations whose sole basis is the internet have...

Words: 2700

Pages: 5

Views: 140

The Natural Organizational Model and the Informal Groups

The nature of an organization is based on different factors such as the environment it is set up in. also, the type of activity it undertakes. This paper will examine the natural organizational model, the informal...

Words: 3009

Pages: 10

Views: 241

Why Pinkberry should focus on making orange and yellow the two prevailing colours

The fact that Pinkberry has evolved from a storefront to a nationally recognized brand makes this franchise of frozen dessert yogurt shops an example to be followed. Yes, the personality of a brand created a platform...

Words: 582

Pages: 2

Views: 95

Ford Motors: Board Presentation For Electric and Hybrid cars Production

Executive Summary The motor vehicle industry in America and worldwide is highly competitive with major players no longer enjoying the dominance that they had had before. Innovation and identification of trends...

Words: 1088

Pages: 4

Views: 131

Home Remodel Project Plan

Project Overview Home remodeling is one of the notable key projects undertake through project management, as a project manager is expected to come up with a clear plan that would help in meeting the expected...

Words: 2152

Pages: 8

Views: 70

How Airbnb Achieved Success

Hospitality industry includes firms that provide lodging and dining services for customers. Many of the businesses in the travel and hospitality industry offer customers with prepared meals, accommodation, snacks,...

Words: 906

Pages: 3

Views: 65

illustration

Running out of time?

Entrust your assignment to proficient writers and receive TOP-quality paper before the deadline is over.

Illustration